Work is underway at the northwest corner of Wilshire and La Brea to prepare a staging yard for the Purple Line Extension. The project contractor, Skanska Traylor Shea, is constructing a temporary alley between Carling Way and Detroit Street. The new alley will redirect traffic west to Detroit, closing the alley exit to La Brea permanently for the remainder of the project.
Later this month, the artwork on the exterior of the former Metro Customer Service Center will be removed and stored for future use at another Metro location. Demolition of the Service Center, the former Blockbuster store, and the former Lawrence of La Brea rug store will occur in late June – and sound wall construction will follow.
Another staging yard will be located on the south side of Wilshire Boulevard. Metro plans to take possession of the Bank of America property at the southwest corner of Wilshire and La Brea by the end of May. Mitigation of any interior environmental hazards will be completed before the bank building is demolished. Metro is in the process of acquiring the property to the west of the Bank of America, which houses Albertson’s Wedding Chapel and other businesses. Metro expects to complete this acquisition by Fall 2015.
Wilshire/La Brea subway construction staging sites. [Courtesy Metro]
Click on image to enlarge.
The staging site at the southwest corner of Wilshire and La Brea will be the most active of all the sites required for the construction of the subway extension. All of the dirt from the tunneling operation – from Western Avenue to La Cienega Boulevard – will be conveyed underground to this location for removal. The site will also house a plant to manufacture the grout that will seal the concrete tunnel lining.
In April, officers of the Miracle Mile Residential Association met with representatives of Metro and the contractor, Skanska Traylor Shea, to discuss noise mitigation at the staging sites, haul routes, and work hours. The MMRA is closely monitoring all aspects of the subway construction and continues to staunchly oppose nighttime work.
The MMRA has requested that Metro make the Bank of America parking lot available to residents and nearby businesses for as long as possible. The east end of the Miracle Mile is experiencing a sharp decline in available parking created by Metro’s activities and the construction of large infill apartment projects on the surface parking lots behind the Desmond’s and Dominguez-Wilshire buildings.
Unfortunately, this request has been complicated by a violent robbery that occurred at this location on May 7. This crime prompted the Bank of America to close the parking lot. The MMRA will make every effort to work with Metro and the L.A.P.D. to enhance safety and security measures so that this parking lot can be re-opened until such time that Metro requires its fulltime use as a construction staging site.
Metro will hold its next Purple Line Extension community meeting on Thursday, May 21, 5:30 PM at the Temple Beth Am, 1039 S. La Cienega Boulevard.
For additional information: